Once the building opens, the operations team will work with design decisions every day: cleaning surfaces, maintaining equipment, fixing faults and replacing worn elements. Incorporate their experience into the brief before those decisions become expensive to change.
For me, one of the most useful early conversations concerns what already causes problems in operating buildings. Which items fail frequently? What is difficult to clean? Which spare parts take too long to find? Specific answers help define requirements for the new project.
Gather the future operations team’s experience
Ask the operations team for two lists. The first covers equipment, inventory and components they buy regularly and that perform well in their conditions. The second covers items frequently repaired, replaced, losing their appearance or proving difficult to maintain.
Identify the cause for each problematic item: intensity of use, unsuitable construction, poor access, cleaning requirements, scarce parts or a mismatch with operating conditions. Where available, add repair records, actual replacement frequency and downtime. An employee’s impression is a useful signal; data helps establish the scale of the problem.
Turn observations into requirements
‘This is difficult to maintain’ should become a specific question for the designer or supplier. Is there enough access space? How can a replaceable component be removed? Can repairs be made without damaging finishes? Which tools and personnel are required? Check the answers against the manufacturer’s technical requirements and the intended operating conditions.
Apply the same review to finishes and fittings. Consider cleaning methods, durability under the planned use, repairability and replacement availability. Standardising selected items may simplify spare stocks, but suitability for the particular space must be confirmed.
Compare costs over the period of use
Purchase price is only one part of the decision. For significant alternatives, also assess installation, resource consumption, servicing, consumables, replacement and possible downtime. Use the same comparison period and assumptions for every option.
Check suppliers’ running-cost information against the intended operating pattern. Where exact figures are unavailable, consider several scenarios and show which factors have the greatest effect. This distinguishes a demonstrated advantage from an assumption.
Illustrative example
A service component is designed behind a continuous finished surface. It needs maintenance access, and replacing one of its elements requires additional clearance. Discovering this after completion would mean altering the finishes. During design, the team can check access, select a suitable solution and coordinate it with the architect and relevant engineer.
Prepare handover early
Before construction finishes, define the documents, settings and knowledge the operations team needs. Depending on the system, these may include operating instructions, equipment documentation, as-built drawings, test results, maintenance schedules, warranty details, service contacts and staff training.
Plan handover by system, with named owners and deadlines. The team needs to understand how to operate the equipment and whom to contact when a fault occurs. Record early observations after occupation: they provide a basis for adjustments and future projects.
Checklist before approving a solution
- The operations team has provided requirements and experience from operating buildings.
- Maintenance access and the ability to replace components have been checked.
- Servicing, consumables and spare-part availability are understood.
- Costs are compared over the same period and operating pattern.
- Documentation, training and responsibility for system handover are defined.