How to review a contractor’s quotation before agreeing the price

What to check in the scope, quantities and rates to understand the full price and prepare well-founded questions for the contractor.

Founder of KERNAVO · 10 years of construction project management experience

When a client receives a quotation, the first question usually concerns the total: is it expensive or reasonable? I begin by checking exactly what the contractor promises to deliver for that money. Without this, even an accurate comparison of rates can lead to the wrong decision.

The same work description does not necessarily mean the same scope. An item called ‘partition construction’ can involve different systems, materials, heights, numbers of layers, surface preparation and rules for measuring openings. Compare prices after clarifying these conditions.

Start with the scope of work

Ask the contractor to link the quotation to specific drawings, specifications or an agreed description of the result. The boundaries should be clear: what the work includes, what the client provides and what will be charged separately. Pay particular attention to delivery, unloading, lifting, substrate preparation, consumables, protection of adjacent surfaces and cleaning.

If labour and materials are presented as one amount, request a breakdown. When the contractor offers only a combined price, record the exact scope of the package and the material specifications. An invented split between labour and materials merely creates an appearance of precision.

Check quantities and units of measurement

Key quantities need a traceable basis: current drawings, a schedule of quantities or agreed site measurements. Check how openings, reveals, edges, junctions and waste are treated. Also look for operations included in a composite rate and charged again as a separate item.

One item measured in square metres may refer to the area of a structure; another may refer to the area of its finished surfaces. Comparing them without clarifying the measurement rule is misleading. If a quantity is provisional, establish who will confirm it, when and on what basis.

Check the basis for assessing the price

A conclusion about the price requires comparable quotations or a verified cost calculation reflecting the actual conditions. Consider location, quotation date, access to the work area, complexity, quantities, programme, material specifications and payment terms. A published price list can provide a reference point, but it must be checked against these factors.

Clarify which taxes and associated costs are included, how long the quotation remains valid and when the price may change. Where evidence is missing, state the limitation precisely: ‘To assess this item, we need to clarify its scope and obtain a comparable quotation.’

Illustrative example

Two contractors quote for partitions. The first includes lifting materials and preparing joints for subsequent finishes. The second treats these operations as extras. Until their cost is clarified, the client is comparing different packages. First bring both quotations to the same deliverable, then assess the price difference.

Record the review outcome

The review should produce clear questions and an updated quotation. For each disputed item, identify what needs explanation, which information is required and how the answer will affect the decision. This gives negotiations a concrete basis and helps document the agreed scope.

Checklist before approval

  • The deliverable and boundaries of every work package are unambiguous.
  • Quantities have a verifiable basis and clear measurement rules.
  • Included and additional costs are listed separately.
  • Price comparisons use the same scope and execution conditions.
  • Quotation validity, payment terms and the process for price changes are defined.