What to check in design documentation before starting work

How to check the drawings for a specific work package, identify inconsistencies and prepare clear questions for the designer before the crew starts.

Founder of KERNAVO · 10 years of construction project management experience

Having a folder of drawings does not establish whether the documentation is ready for a particular task. The contractor needs current, coordinated information: where to work, the dimensions and levels, the materials forming the construction and its interfaces with adjacent systems.

Before work starts, I suggest checking readiness by work package. Partitions, floors, water services and electrical work require different information. The review should establish what is defined, what needs clarification and which unresolved matters prevent execution.

Identify the current revision

Create a document register for the relevant area or package. Record each document’s title, number, revision, date, status and person responsible for issuing it. Confirm that the client, contractor and specialists use the same set and that superseded sheets are marked as obsolete.

A file date alone is insufficient: a newer document may still be an interim issue. Its permitted use and the procedure for issuing it for construction must be clear. Notify affected participants of changes and explain which previous decisions they replace.

Check the information needed for the specific work

For partitions, check locations, setting-out dimensions, thicknesses, construction types, heights, openings, junctions and required performance. For floors, check levels, build-ups, finish thicknesses, transitions, thresholds and wet-area details. Clarify whether a level refers to the structure, preparation layer or finished floor.

Water and drainage systems need coordinated equipment connections, routes and the necessary level information. Electrical work needs consumer locations, requirements, connection points, distribution boards and cable routes. The relevant designers determine the precise information needed for the work; the project manager organises the completeness review.

Check interfaces between disciplines

Pay particular attention to services passing through structures, equipment positions relative to the layout, ceilings and service routes, and access to engineering components. The agreed layout should be reflected consistently in related drawings.

Refer identified inconsistencies to the responsible designer. The installer needs a documented solution that can be applied unambiguously on site. An oral agreement without updated working information risks leaving other participants using the previous version.

Illustrative example

A sanitary fixture has been moved on the bathroom plan, while the services drawings remain at the previous revision. The floor build-up is also being finalised. Before the related work begins, the location, connections and levels must be coordinated. Otherwise, each installer may carry out their own work correctly using different starting information.

Prepare a request with a specific expected outcome

State the area, document numbers and revisions, the discrepancy and the work it affects. Request a specific output: an updated detail, confirmed level or revised drawing. Add the response date required by the programme. The response should lead to a decision with a clear status that is communicated to the installers.

If documentation is still being developed, list ready and blocked packages. Assign an owner, required output and deadline to every blocker. Authorised participants confirm whether individual works can start, taking account of technical, organisational and applicable permitting requirements.

Documentation readiness checklist

  • The current document set and its construction issue status are defined.
  • The selected package has the necessary dimensions, levels, details and specifications.
  • Interfaces with adjacent structures and building services have been checked.
  • Open questions have an owner, deadline and clear expected output.
  • Participants have received documented decisions and know which drawings were superseded.