- Unknown should never default to zero.
- Assess change across multiple dimensions and alternatives.
- Conditional decisions need limits and a defined re-approval point.
Unknown should be recorded as unknown
If exact cost or schedule effect is not known, do not default to zero. Zero is a positive statement that impact was assessed and found absent.
Use unknown/to assess with an owner and clarification deadline.
Separate known and unknown parts
The team may know the extra quantity and material while lead time or interface impact remains uncertain.
Do not block all assessment because one dimension is unknown. Record known facts and open consequences separately.
Assess across several dimensions
Review scope, time, money, quality, safety, permits, operations and affected participants. Small cost changes can create critical schedule effects.
Also check already executed or accepted results and whether re-verification is required.
Decisions can be conditional
An authorised role may sometimes allow a limited part of the change before full assessment, such as preparation or capped procurement.
Define permitted scope, limit, assumptions and the point at which a new decision is required.
Alternatives are part of assessment
Do not treat a change as a binary accept/reject question. Compare retaining the baseline, resequencing, material substitution or delaying the decision.
The best project outcome is not always the cheapest local option.
Unknown impact should enter the forecast
If a change is likely to create cost or delay but exact value is not known, reflect it as a range, scenario or explicit uncertainty.
Otherwise EAC and completion date stay artificially optimistic until the impact becomes unavoidable.
Technical agreement is not automatic approval of every consequence
A specialist may approve the technical solution within their subject without authorising extra budget or contract change.
Each affected dimension follows its authority route before the overall decision is sanctioned.
Update the baseline when the uncertainty is resolved
Unknown cannot remain permanent. By the stated date, quantify the effect or escalate the inability to assess it.
After approval, update the controlled baseline while preserving assumptions and decision history.