Public methodology note

A chat message is not yet a management decision

“OK, let’s do it that way” in chat can mean agreement, advice, instruction, assumption or simply acknowledgement. If the project does not distinguish these meanings, one participant later treats it as approved while another remembers only an informal discussion.

15 October 2026MEGAPROJECT / Methodology8 min read
Key points
  • The communication channel does not define decision status.
  • Author authority matters more than confident wording.
  • Significant decisions should become traceable rather than remain in chat.
01

A message is an information carrier, not a decision type

The same chat carries photos, facts, assumptions, requests, tasks and decisions. The channel does not define management status.

Classify what actually happened: obligation, instruction, approval or just a question for analysis?

02

A decision needs an authorised role holder

A clear instruction is still not a valid basis if it came from someone outside the relevant authority. “The investor asked” or “the designer told the crew” does not always mean a change is authorised.

Control needs the author’s role and authority boundary, not only the text.

03

Unilateral decision and multi-party agreement are different

An authorised role may decide independently within a defined limit. That does not need to be artificially turned into a multi-party agreement.

Where several approvals are required, one person’s answer does not complete the decision route.

04

Significant decisions should leave a trace

Not every “OK” belongs in a register. But if it changes scope, time, cost, requirement, responsibility, sequence or result criteria, it should become a traceable management object.

Minimum: what changed, who had authority, when it became effective and what action follows.

05

An instruction without a defined result is only half a decision

“Peter, solve the door issue by Friday” has an owner and date but not a clear completion criterion. Approved specification? Purchase order? Technical decision?

Actions close objectively when expected result or confirmation is defined.

06

A chat-based change should enter change control

If the conversation changes the baseline, a screenshot is not enough. Assess impact, authorise the change and update the controlled baseline.

Chat may be the source of an initiative or evidence of communication, but it should not be the only home of a critical change.

07

The goal is not more minutes; it is less lost management memory

A strong system does not copy every sentence. It extracts the events that actually affect management.

The team then spends less time arguing over what someone meant and more time acting on current decisions.