- Budget is not payment; contract is not execution.
- Invoice and approved payment are different states.
- Financial events should link to specific work and evidence.
Budget is a limit and model, not an expenditure fact
An approved budget describes planned or authorised cost by structure. It does not mean the money is contracted, available on a given date or payable.
Estimates need measurable scope, quantities, rates, price date, inclusions and exclusions. Unknown quantities should remain visible as uncertainty.
Tender offer and contract value are different states
A bidder’s offer can change after scope clarification, exclusions and negotiation. Only an agreed contractual basis creates a defined commitment.
Keep estimate, bid, approved budget and contract value separate or plan-versus-actual reporting starts from different baselines.
Commitment is not execution
A signed contract reserves part of the budget but does not prove physical delivery. A project may have high committed cost and low actual progress.
Cash forecasting therefore needs future liabilities under signed commitments, not only historic payments.
Executed value needs an agreed evidence basis
Confirmed execution should rely on measured quantity, accepted result, milestone or another contractual basis. “The contractor says we are 80% done” is not a financial fact by itself.
Production and financial status should be linked without being collapsed into the same state.
An invoice is a payment request, not proof of entitlement
An invoice may arrive before quantities, documents or contract conditions are fully verified. Invoice, approved payment and paid are separate states.
Treating every invoice as actual cost can distort cash flow and remaining-budget views.
Payment is only one financial event
Cash leaving the account matters for cash flow, but it does not fully describe project economics. An advance may be paid before work, while accepted work may still be unpaid.
Track advances, commitments, accepted execution, invoices, approved payments and actual payments separately.
Client budget and contractor internal cost are different perspectives
The client’s budget, contractor revenue and contractor internal cost are different financial views. Agreeing a price does not automatically disclose margin.
Shared systems therefore need connected data with controlled visibility rather than automatic financial transparency between parties.
Manage the chain of financial states, not one “spent” number
A useful chain is budget → tender/estimate → contract/commitment → confirmed execution → invoice → approved payment → paid → remaining forecast.
Linked to work packages, this shows not only how much money moved but what it relates to, why it is due and where overrun risk is forming.