- A problem is not an approved change.
- Correcting your own defect is not automatically new paid scope.
- Assess changes across time, money, quality, safety and wider impact.
Start with the current baseline
To decide whether work is additional, know what was agreed before the proposed change: drawing, specification, scope, contract term or result criteria.
Without a baseline, the discussion becomes competing memories of what each side “meant”.
A change alters an agreed parameter
If a proposal changes scope, requirement, sequence, contractual condition, resource boundary or another baseline parameter, it may be a change. It still needs description and assessment.
Something becoming harder or more expensive for the contractor does not by itself prove that the obligation changed.
A defect may trigger a change request but is not itself an approved change
A defect may require a new technical solution, but until authorised it remains a problem and potential trigger for a decision.
Separate correcting a non-compliant result from the client changing the desired result.
Correcting your own defect does not automatically become payable extra work
If the executor owed a defined result and delivered a defective one, correction should not automatically be relabelled as new paid scope merely because it requires extra resources.
Legal consequences depend on contract and law, but management should at least classify the origin correctly.
Assess more than price
A change request should show reason, current baseline, proposed state and impact on scope, time, money, quality, safety, permits, operations and other participants.
A cheap change can create major schedule impact; a simple change can force rework of already accepted work.
Do not confuse assessment with permission to proceed
A contractor can price a change quickly without having authority to execute it. Verbal “do it now, we will sort it later” creates risk for both sides.
A controlled route is identify → describe → assess → authorised decision → revised baseline → execute.
Preserve history
A new revision should not erase the old one. Otherwise the project loses what was originally contracted, when the change arose and what work was performed against the old baseline.
History separates approved variations from disputed work and defect correction.